| Upgrades Planned or In Progress |
| Composting Head | |
| Description | Current Status |
| I've had to clear clogged sewage lines once too often. In December, 2007 I ordered an Airhead composting head. |
The Airhead was delivered in March, 2008. I have created a web page on
the installation here. The installation of the toilet was completed on May 31, 2008 and it is now in operation. |
| Engine Box Rebuild and Sound Insulation | |
| Description | Current Status |
|
Sound proofing is almost non-existent on Sarah's engine compartment. With
the engine running it is almost impossible to monitor or converse over the
SSB or VHF radios. The engine compartment box has some vestigial sound
proofing material that looks to be part of original (1978) equipment. There
is no sound proofing of the rear and sides of the engine compartment. With the completion of the repower a new engine box is now a necessity. |
I have published a web page to cover the rebuilding of the engine box. |
| New Sails | |
| Description | Current Status |
|
Re-cut the staysail so that it does not overlap the shrouds. Add a mizzen staysail. |
Quantum Solomons Loft re-cut the staysail in February, 2008. I've now
got to figure out how to rig it. This will require putting two short
pieces of genoa track on the coach roof. The more difficult problem is
how to rig the sheets for this sail so it can be trimmed by the mainsheet
winch. No action on the mizzen staysail as yet. |
| Sun Awning | |
| Description | Current Status |
| Need to build a sun awning to cover the main cabin deck and cockpit while at dock or at anchor | No action |